Why Should You Prepare For Your PRINCE2 7 Foundation written Exam With MyCertsHub?
At MyCertsHub, we go beyond standard study material. Our platform provides authentic PRINCE2 Prince2-Foundation Exam Dumps, detailed exam guides, and reliable practice exams that mirror the actual PRINCE2 7 Foundation written Exam test. Whether you’re targeting PRINCE2 certifications or expanding your professional portfolio, MyCertsHub gives you the tools to succeed on your first attempt.
Verified Prince2-Foundation Exam Dumps
Every set of exam dumps is carefully reviewed by certified experts to ensure accuracy. For the Prince2-Foundation PRINCE2 7 Foundation written Exam , you’ll receive updated practice questions designed to reflect real-world exam conditions. This approach saves time, builds confidence, and focuses your preparation on the most important exam areas.
Realistic Test Prep For The Prince2-Foundation
You can instantly access downloadable PDFs of Prince2-Foundation practice exams with MyCertsHub. These include authentic practice questions paired with explanations, making our exam guide a complete preparation tool. By testing yourself before exam day, you’ll walk into the PRINCE2 Exam with confidence.
Smart Learning With Exam Guides
Our structured Prince2-Foundation exam guide focuses on the PRINCE2 7 Foundation written Exam's core topics and question patterns. You will be able to concentrate on what really matters for passing the test rather than wasting time on irrelevant content. Pass the Prince2-Foundation Exam – Guaranteed
We Offer A 100% Money-Back Guarantee On Our Products.
After using MyCertsHub's exam dumps to prepare for the PRINCE2 7 Foundation written Exam exam, we will issue a full refund. That’s how confident we are in the effectiveness of our study resources.
Try Before You Buy – Free Demo
Still undecided? See for yourself how MyCertsHub has helped thousands of candidates achieve success by downloading a free demo of the Prince2-Foundation exam dumps.
MyCertsHub – Your Trusted Partner For PRINCE2 Exams
Whether you’re preparing for PRINCE2 7 Foundation written Exam or any other professional credential, MyCertsHub provides everything you need: exam dumps, practice exams, practice questions, and exam guides. Passing your Prince2-Foundation exam has never been easier thanks to our tried-and-true resources.
Which statement about the quality review technique is FALSE?
A. It enables a check to be made on a product's fitness for purpose B. It defines the quality responsibilities of the project team C. It supports the management of future changes by providing a baseline for a product D. It is used to gain wider acceptance of a product by involving key interested parties
Answer: B
Question # 2
Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.
A. quality B. supplier C. risk D. product
Answer: B
Question # 3
Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities
A. change budget B. project budget C. project's cost tolerance D. project's risk tolerance
Answer: B
Question # 4
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?
A. Project Brief B. Project Initiation Documentation C. Project mandate D. Benefits Review Plan
Answer: B
Question # 5
Which is part of quality control?
A. Undertake quality reviews B. Write Product Descriptions C. Provide assurance that the project is being conducted properly D. Document the customer's quality expectations
Answer: A
Question # 6
Identify the missing word in the following sentence. The guiding obligations and good practices that determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.
A. Principles B. Themes C. Processes D. Techniques
Answer: A
Question # 7
Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity
A. Avoid B. Reduce C. Share D. Transfer
Answer: C
Question # 8
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
A. Configuration Item Record B. Quality Register C. Highlight Report D. Checkpoint Report
Answer: D
Question # 9
Which should be funded by a change budget?
A. Increase in agreed scope B. Increase in agreed scope C. Increase in agreed scope D. Handover activities
Answer: A
Question # 10
Which should be provided by corporate or program management before the Starting up a Project process commences?
A. A Project Brief B. Sufficient information to identify the prospective Executive C. The Project Initiation Documentation D. Authority to initiate a project
Answer: B
Question # 11
Whose approval is needed to replace a Stage Plan with an Exception Plan?
A. Corporate or programme management B. Project Board C. Project Manager D. Team Manager
Answer: B
Question # 12
What is an off-specification?
A. A new requirement B. A quality tolerance C. A type of issue D. A major risk
Answer: C
Question # 13
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?
A. Benefits B. Quality C. Risk D. Scope
Answer: B
Question # 14
Which is NOT one of the PRINCE2 integrated elements?
A. Tailoring PRINCE2 to the project environment B. The processes C. The products D. The themes
Answer: C
Question # 15
Which is the Issue Register NOT used for?
A. Capture external events that are impacting a stage B. Record information about a deviation in stage tolerance C. Capture any threats or opportunities that might have an impact on a stage D. Record any problems identified when authorizing a Work Package
Answer: C
Question # 16
Which is a purpose of the Risk Register?
A. Describe the risk management techniques and standards to be applied to the project B. Act as a central record of information relating to the identified risks for the project C. Act as a repository for informal issues D. List the responsibilities for achieving an effective risk management procedure
Answer: B
Question # 17
Which is NOT considered when defining risk tolerance?
A. A Project Board's attitude towards risk-taking B. The allocated risk budget C. An organization's risk appetite D. The amount of risk a Project Board considers acceptable
Answer: B
Question # 18
Which process covers the work done by external suppliers who may NOT be using PRINCE2?
A. Closing a Project B. Managing a Stage Boundary C. Managing Product Delivery D. Directing a Project
Answer: C
Question # 19
Which statement about the Directing a Project process is true?
A. Provides a mechanism for the Project Board to assure that there is a continued business justification B. Covers the day-to-day activities of the Project Manager C. Ensures there are regular progress meetings D. Begins on completion of the Initiating a Project process
Answer: A
Question # 20
How many management stages should a PRINCE2 project consist of?
A. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project B. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage C. Initiation stage and at least one other management stage to cover the remainder of the project D. Start up stage, initiation stage and a closing stage
Answer: C
Question # 21
Which is a task of product-based planning?
A. Identify activities and dependencies B. Write the Project Product Description C. Prepare the Work Packages D. Produce Product Status Accounts
Answer: B
Question # 22
Who should act as the communication channel between a project and corporate or programme management?
A. Project Board B. Project Assurance C. Project Manager D. Project Support
Answer: A
Question # 23
Which is a purpose of the Starting up a Project process?
A. Provide information so a decision can be made asto whether a project is viable and worthwhile to initiate B. Define the means of communication between the project and corporate or programme management C. Define the project controls D. Record any identified risks in the Risk Register
Answer: A
Question # 24
Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.
A. a corporate B. a temporary C. an external D. a technical
Answer: B
Question # 25
Which is a true statement about PRINCE2 event-driven controls
A. Event-driven controls take place at predefined periodic intervals B. Event-driven controls are produced at the frequency defined in a Work Package C. Event-driven controls are used for decision making D. Checkpoint Reports are event-driven controls
Answer: C
Feedback That Matters: Reviews of Our PRINCE2 Prince2-Foundation Dumps
Nakul SalviFeb 02, 2026
Thanks to Mycertshub's study materials, preparing for the PRINCE2-Foundation exam felt organized and straightforward. Before the actual test, I was able to gain a solid understanding of project management principles thanks to the thoughtful design of each question.
Théodore FortinFeb 01, 2026
When I started practicing for the PRINCE2-Foundation exam, everything started to make sense. I was nervous about the exam. Studying went much more smoothly than anticipated due to the materials' clear organization and smooth transitions between subjects.
Lore GroßFeb 01, 2026
The PRINCE2-Foundation resources on Mycertshub made exam preparation fun and efficient. The fact that the practice tests and dumps were based on actual exam logic gave me a real boost of confidence and comprehension.